Planning

Welsh planning law set for major shake-up

Welsh planning law set for major shake-up

The Law Commission has proposed a wide-ranging shake-up of planning law in Wales. A report published this week calls for more than 190 technical reforms.

New primary legislation in the shape of a planning act is expected to carry through the changes, designed as the centrepiece of a fresh planning code for the country.

The report found that the legislation governing the planning system in Wales was “confused and unhelpful”. It has been much amended and supplemented over the past 30 years, is full of obsolete provisions and does not meet current best practice.

The report contains 193 recommendations to simplify the legislation and make it fit for purpose. These include:

  • making clear the principles underlying the planning system in Wales;
  • simplifying the law in respect of when planning permission is required;
  • clarifying the status of outline planning applications;
  • tightening up the law on pre-commencement conditions;
  • enabling planning obligations to be entered into by prospective purchasers;
  • rationalising penalties for breaches of planning control;
  • simplifying the authorisation of works to listed buildings;
  • enabling landowners to discover when they need various special consents;
  • enabling authorities to remove unauthorised advertisement hoardings;
  • tightening up control over works to protected trees;
  • simplifying the law on High Court challenges; and
  • clarifying the definition of some technical terms.

The commission has also proposed the repeal of unused legislative provisions such as those relating to planning inquiry commissions, simplified planning zones, enterprise zones, new towns, urban development corporations, rural development boards, archaeological areas and advertisement appeals tribunals.

“Most of these have not been used for 30 years or more and some have never been used at all,” commented the commission.

The Welsh Government will provide an interim response to the report by the end of May 2019, and a detailed response by the end of November 2019.

The commission published a consultation paper a year ago. The overall response to its proposals was strongly favourable.

The report and more information can be found on the Law Commission website.

Planning Success

Planning Success

Always great to finish the week with a positive note: ICE Arch Ltd were so excited to hear that Planning Approval has been granted for the conversion of these Barns under Class Q Permitted Development Rights. We have been collaborating with Planning Consultant Helen Howie from Berrys Chartered Town Planners to gain consent for 5 dwellings. Prior Approval for Barns in the Greenbelt is difficult so this is a fantastic achievement.

It’s better to appeal than re-apply

It’s better to appeal than re-apply

The reason is quite simple.  40% of rejections are reversed on appeal, a higher success rate than amended applications.  And, of course, appealing is more cost-efficient than preparing and submitting an amended application.

The survey concluded that the high success rate of appeals is almost certainly caused by an absence in some areas of up-to-date local plans.  If authorities do not have an up-to-date local plan and are unable to demonstrate that at least five years’ worth of land has been allocated for local housing, then development on sites that could or should have been allocated to this need are very likely to succeed on appeal if initially rejected.

The Neighbourhood Planning Act 2017 requires planning authorities to set out policies addressing strategic land use priorities as well as identifying housing sites which will deliver at least a five-year housing supply.  If these plans have not been made by April 2018, then the secretary of state has the power to intervene and take the preparation of local plans out of the hands of a single authority or, as a last resort, start this work on behalf of the council.

From the Planning Department viewpoint, appeals are evidence of a system that requires immediate change.  Better consultation and up-to-date plans would ensure such applications get through first time, without the extra effort and delay.

Other interesting facts came to light in the survey.  Three-quarters of the builders surveyed buy more land with pre-existing planning permission than they did 10 years ago. Almost four-fifths place speeding up planning decisions at the top of a wish list for regional devolution, urging mayors to unlock stalled sites in their areas.

When is a Green Gap not a Green Gap?

When is a Green Gap not a Green Gap?

When Cheshire East Borough Council lost a legal battle at London’s Court of Appeal in relation to a planning inspector’s approval for the new homes in a Green Gap at Willaston it had implications for green belt; protection of the countryside; conserving the landscape; Areas of Outstanding Natural Beauty; National Parks; conservation of wildlife or cultural heritage; protecting the local environment.

Paragraph 49 of the NPPF says that “relevant policies for the supply of housing should not be considered up-to-date if the local planning authority cannot demonstrate a five-year supply of deliverable housing sites.”

Since the council was unable to demonstrate a five-year housing land supply, the inspector decided that the council’s green gap policy could not be considered up to date and should be disapplied.

A High Court judge found that the planning inspector had been wrong to regard the green gap housing policy as one that was out of date. However, the Court of Appeal disagreed and said the inspector had “made no error of law.” and upheld the planning inspector’s decision.

The Court of Appeal ruling said: “Our interpretation of the policy does not confine the concept of
‘policies for the supply of housing’ merely to policies in the development plan that provide positively for the delivery of new housing in terms of numbers and distribution or the allocation of sites.

“It recognises that the concept extends to plan policies whose effect is to influence the supply of housing land by restricting the locations where new housing may be developed – including, for example, policies for the green belt, policies for the general protection of the countryside, policies for conserving the landscape of Areas of Outstanding Natural Beauty and National Parks, policies for the conservation of wildlife or cultural heritage, and various policies whose purpose is to protect the local environment in one way or another by preventing or limiting development.

“It recognises that the concept extends to plan policies whose effect is to influence the supply of housing land by restricting the locations where new housing may be developed – including, for example, policies for the green belt, policies for the general protection of the countryside, policies for conserving the landscape of Areas of Outstanding Natural Beauty and National Parks, policies for the conservation of wildlife or cultural heritage, and various policies whose purpose is to protect the local environment in one way or another by preventing or limiting development.

Read more at: https://www.linkedin.com/pulse/developer-wins-landmark-case-over-cheshire-green-gap-policy-marsh

“It reflects the reality that policies may serve to form the supply of housing land either by creating it or by constraining it – that policies of both kinds make the supply what it is.”

More Homes in East Cheshire

More Homes in East Cheshire

More homes is a feature of Cheshire East Council’s revised local plan strategy, due to be approved by the full council later this month before a further round of public consultation is carried out. This will include additional and amended strategic site allocations.

The strategy revisions reflect a revised housing requirement of 36,000 homes (up from 29,000) and an increased employment land requirement, up from 300-hectares to 380-hectares, to reflect the stronger anticipated jobs growth rate of 0.7 per cent per.

eastcheshire

 

 

New Homes needed in Cheshire East

New Homes needed in Cheshire East

The number of new homes needed in Cheshire East is 36,000, according to the Council’s draft local plan.

The planning inspector examining Cheshire East Council’s the plan is broadly supportive of the local planning authority’s latest work.

The inspector noted that the council has produced “an impressive and comprehensive set of additional evidence within a relatively limited amount of time during the suspension of the examination.” The inspector said the council had adopted a balanced and rational approach to economic and jobs growth.

On housing, the objectively assessed need (OAN) for 36,000 new homes was viewed as “supported by the evidence”.

The Local Plan sets planning policies and allocates sites for development. It is the Statutory Development Plan for Cheshire East and is the basis for deciding planning applications. A new Local Plan for Cheshire East is currently being prepared and will guide development up to 2030.

The Plan covers a range of matters including the number of new homes that are needed and where they should be located; the amount and location of new employment land; protection and improvement of important open areas and provision of new ones; provision of new infrastructure and improvement of town centres and community facilities in the Borough.

You can read about the plan at https://portaldirector.wordpress.com/2015/12/16/planning-round-up-17-december/

CheshireEast

Change of Use of Agricultural Buildings

Permitted Development Rights for the Change of Use of Agricultural Buildings

This year ICE Arch Ltd has been successful in gaining – Prior Approval for the Proposed Change of Use of an agricultural building into two dwellings.  The client is thrilled that they are able to make better use of a redundant building.

The changes to planning came into force on 6th April 2014 making it easier, in planning terms, to convert redundant agricultural buildings into residential dwellings.  The then planning minister, Nick Boles, said this would make, ‘better use of redundant or under-used agricultural buildings’ without taking up countryside.

This was certainly beneficial to our client.

What new uses can an agricultural building change to?

There are 3 main uses to which an agricultural building can change under permitted development rights. They are to:

  • flexible use (shops; financial and professional services; restaurants and cafes; business; storage or distribution; hotels; assembly and leisure)
  • educational use (state-funded school; registered nursery)
  • residential use (up to 3 dwellings)

There are size thresholds, limitations and conditions associated with the rights.  Should you have a project in mind or require advice on how to convert an agricultural building we would be happy to help.

Cheshire East may need to submit amended local plan

Cheshire East may need to submit amended local plan

After concluding it had not dealt adequately with either housing assessment and provision or green belt issues, the planning inspector who been examining Cheshire East Council’s draft local plan has warned the planning authority it may have to withdraw the strategy and resubmit it.

He has told the local authority: “Consultation on a significantly amended overall housing and employment land provision figure, along with a set of new or amended sites, may constitute the type of substantial amendment which might suggest that the submitted plan should be withdrawn and resubmitted when all necessary community engagement and public consultation has been completed.”

RIBA Awards

RIBA Awards

What do YOU think of the buildings that are in receipt of the RIBA’s 2015 awards ?  View them here

RIBA Awards Flint House